Project 46

[ Next | Last | Contents ]


1. Project Title: Paint Creek Habitat Improvement (Southeast Michigan)

2. Contact

Mr. Mike Thomas

Michigan Department of Natural Resources, Lake St. Clair Fisheries Research Station, 33135 South River Road, Mount Clemens, MI 48045, USA

Tel.: (810) 465-7214; FAX: (810) 465-7504

Mr. Ron Spitler

Michigan Department of Natural Resources, Southeast Michigan District Office, 38980 Seven Mile Road, Livonia, MI 48152, USA

Tel.: (313) 953-0241; FAX: (313) 953-0243

Mr. Dave Cozad

Mainstream Resources, 947 West Midland Rd., P.O. Box 96, Auburn, MT 48611, USA

Tel.: (517) 662-4472; FAX: (517) 662-7618

Mr. Allen Pienkowski

Clinton Valley Trout Unlimited, 830 Merton, #102, Detroit, MI 48203, USA

Tel.: (313) 341-1915

3. Agencies Involved

Michigan Department of Natural Resources

Local chapters of Trout Unlimited

Michigan Department of Corrections field crews

4. Restoration Goal

To enhance brown and brook trout stream habitat with wooden structures and to stabilize shorelines.

5. Project Type

Construction of "lunker" structures and other log structures; stabilize shorelines.

6. Background and Rationale

Paint Creek is one of the few trout streams in Southeast Michigan. Bank erosion problems were documented in a number of reaches of Paint Creek in Oakland County and local chapters of Trout Unlimited were interested in undertaking habitat enhancement and rehabilitation.

7. Regulatory Considerations

A permit was required under the Inland Lakes and Steams Act (Act 346).

8. Criteria

Stabilize eroding banks and enhance fish habitat.

9. Project Design

The project was designed to address some of the worst areas of erosion in Paint Creek that would also benefit from enhanced fishery habitat. "Lunker" structures are designed to simulate undercut banks and are most often installed on the outside bank in a stream meander (Figure 1). These structures typically provide 61 m of 15-30 cm deep cover simulating an overhanging bank. Because the area behind the structure is backfilled with rock, these structures can also be utilized to stabilize the toe of eroding banks in fairly stable streams. Paint Creek was scouring laterally into highly organic soils. Placement of the "lunker" structures served to stabilize the streambank, halt stream sedimentation, and provide cover for resident trout.

10. Implementation

For a number of years, early 1980's and onward, local Trout Unlimited Chapters, co-ordinated by the Clinton Valley Chapter, have worked together in a 0.8 km stretch of Southeast Michigan's best trout stream (i.e., Paint Creek). Shoreline stabilization with rock, "lunker" structures and other log structures have enhanced that section of the stream.

"Lunker" structures are typically built in 2.4 m sections and range in width from 1.2 to 1.8 m. Most often the structures are constructed of 5 cm oak planking with 15-20 cm spacers. Six spacers are placed between the top and bottom decks of each structure and the section is then held in place by nine 1.5 m sections of 16 mm rebar. The structures are prefabricated in sections on land and then assembled streamside.

These "lunker" structures can be installed with two person crews and hand tools. Trout Unlimited volunteers and Michigan Department of Corrections crews installed approximately 53 m of lunker structure with 50 m3 of fieldstone backfill.

Professional planning is required to ensure that stream restoration efforts are truly meaningful and enduring.

11. Degree of Environmental Intervention

No adverse impacts were noted during lunker installation; however, original log structures (i.e., logs placed vertically at toe of bank to anchor other logs placed horizontally along bank) were pried loose by ice and high flow conditions, and resulted in log jams which had to be removed.

12. Materials and Cost

The following materials are required to construct one 2.4 m lunker section:

22 m of 5 ¥ 15 cm rough sawn oak planking;

2.4 m of 10 ¥ 35 cm oak;

90 cm of 15 cm diameter cedar post for spacers;

14 m of 16 mm rebar;

1.1 kg of 15 cm spikes; and

3 m3 of fieldstone rip-rap.

Approximate material cost per 2.4 m section was $115.00.

Approximately 0.5 person-days are required to fabricate and install one 2.4 m section, given reasonable stream access. As access becomes more difficult, installation costs will increase.

13. Biological Assessment

Fishery surveys are performed every 3-5 years on Paint Creek; however, these surveys do not allow for quantification of project effectiveness (evaluation of project effectiveness relative to the fishery would require a greater spatial and temporal sampling frequency; variability in urban steams is high).

14. Measures of Success

Success Rating: 4 - successfully installed a number of "lunker" structures which have resulted in bank stabilization, decreased erosion, and physical habitat enhancement.

15. Key References

Hunter, C.J. 1991. Better trout habitat: a guide to stream restoration and management. Montana Land Reliance (TSBN 0-93328078-5).


Correct citation for this contribution:

Thomas, M., Spitler, R., Cozad, D., and Pienkowski, A. 1995. Paint Creek habitat improvement (Southeast Michigan), p. 287-290. In J.R.M. Kelso and J.H. Hartig [editors]. Methods of modifying habitat to benefit the Great Lakes ecosystem. CISTI (Can. Inst. Sci. Tech. Inf.) Occas. Pap. No. 1.