Civil Design Services for Giant Mine Remediation Project

Fairness Monitor Contractor's Final Report

September 9, 2013

Submitted to: Director General, Operational Integrity Sector

Submitted by: Knowles Consultancy Services Inc. and Hill International Inc. in Joint Venture

PDF Version ( 63KB)
Help with Alternative Formats

Table of Contents

  1. Background and Introduction
  2. Project Requirement
  3. Attestation of Assurance
  4. Objectives of the Fairness Monitor Assignment and Methodology
  5. Fairness Monitor Specific Activities and Findings
  6. Reference Documents

Background and Introduction

Knowles Consultancy Services Inc. and Hill International Inc. in Joint Venture was engaged as the Fairness Monitor (FM) to observe the competitive procurement processes required for long term contracts to support the Giant Mine Remediation Project undertaken by Public Works and Government Services Canada (PWGSC).  Knowles Consultancy Services Inc. and Hill International Inc. in Joint Venture is an independent third party with respect to this activity.

The Giant Mine Remediation Project in Yellowknife, North West Territories, requires a number of support services and design services contracts. The subject of this report is the procurement of Civil Design Services undertaken through Solicitation Number EW702-140228/A.

We hereby submit the Final Report on our activities during the procurement process for Civil Design Services, commencing with a Site Visit and Industry Day held for interested firms covering all consulting support services and design services required for the remediation project, reviews of a draft and final Request for Proposal (RFP), the evaluation of proposals and the selection of the recommended bidder.

This report includes our attestation of assurance, a summary of the scope and objectives of our assignment, the methodologies applied, and specific activities and relevant findings.

Project Requirement

After the owner of the Giant Mine located in Yellowknife in the Northwest Territories went into receivership, the Government of Canada took on the responsibility for the existing environmental liabilities on the Giant Mine property.  Environmental liabilities include 237,000 long tons of arsenic trioxide dust produced during the gold roasting process stored in fourteen chambers underground, eight open pits, 35 openings to the mine, four tailing ponds, and 100 buildings including a roaster house complex that is highly contaminated with arsenic and fibrous asbestos.

An environmental assessment, part of the water licensing process, has recently been completed and is being reviewed by project officials. Remediation planning is underway through advancement of design, development of specifications as well as coordination of the overall remediation work.

Remediation planning involves several phases: care and maintenance contract activities currently underway; contracts specific to time critical site stabilization and supporting services some of which are underway with others imminent; and long term contracts for long term remediation.  Long term remediation includes contracts for environmental support services, mining support services, civil design services, general design services and construction management services. 

The Civil Design Services may include but are not limited to:

  • coordinate overall design elements, identify gaps and linkages between all design packages;
  • investigate, provide cost estimates and develop specifications and drawings to support a Design-Bid-Build project delivery approach for tailings cover;
  • Investigate, provide cost estimates and develop specifications and drawings to support a Design-Bid-Build project delivery approach for surface water management;
  • investigate, provide cost estimates and develop specifications and drawings to support a Design-Bid-Build project delivery approach for Baker Creek remediation; and
  • investigate, provide cost estimates and develop specifications and drawings to support a Design-Build and/or Design-Bid-Build project delivery approach for borrow material to be brought in from other locations within the Giant Mine property.

The Work to be performed under the Contract will be on an “as and when required basis” using Task Authorizations.

Attestation of Assurance

The FM hereby provides the following unqualified assurance statement concerning the procurement process to select a company to provide Civil Design Services for the Giant Mine Remediation Project:

It is our professional opinion that the competitive process we observed was carried out in a fair, open and transparent manner.

______________________________
Roger Bridges
President, Knowles Consultancy Services Inc.
FM Contractor's Representative

_______________________________
Peter Woods
FM Specialist

_____________________________
Bruce Maynard P.Eng.
FM Team Leader

Objectives of the Fairness Monitor Assignment and Methodology

The overall objective was as follows: provide PWGSC with independent observation of project procurement activities; provide fairness related comments to project officials as early as possible so that appropriate action could be taken to resolve the concerns before fairness was impacted; bring any potential fairness concerns to the attention of the Operational Integrity Sector if there is no timely resolution with project officials; and attest to the fairness of the procurement process, including its execution.

To accomplish the objective we undertook the following activities:

  • became familiar with the project governance structure;
  • reviewed Buy and Sell postings regarding the overall Giant Mine Remediation Project along with  observing a Site Visit and Industry Day;
  • reviewed the Request for Proposal (RFP);
  • reviewed all amendments and addenda to the RFP including questions submitted by bidders and answers provided;
  • reviewed the procedures to be used for the evaluation of responses and the guidance provided to the evaluation team;
  • observed the evaluation of responses to the RFP to ensure that the specified evaluation and contractor selection procedures and departmental policy were followed and consistently applied during the evaluation and selection process; and
  • observed the debriefing of unsuccessful bidders. (This activity will be reported on in an addendum to this report after any debriefings.)

Fairness Monitor Specific Activities and Findings

Fairness Monitor Activities and Findings prior to the RFP Posting Period

On August 1, 2012 we observed a Site Visit and Industry Day held in Yellowknife that were held for industry for all required consulting services including civil design services that would be required for the Giant Mine Remediation Project.  Attendees were provided with background information on the project and an outline of the proposed procurement plan including the types of services that would be required.  The attendees were also provided with a tour of the Giant Mine site.  No fairness deficiencies were identified.

On June 25, 2013 we reviewed a draft of the RFP for Civil Design Services.  No fairness deficiencies were identified. 

Fairness Monitor Activities and Findings during the RFP Posting Period

On June 28, 2013 we reviewed the RFP for Civil Design Services (Document 1) as posted on Buy and Sell and during the period July 15, 2013 to August 2, 2013, we reviewed Amendments 1 to 3 (Documents 2 to 4) including questions from interested firms and answers provided.  Fairness related comments were provided and appropriate action taken by project officials. 

On July 19, 2013 we observed the optional Site Visit to the Giant Mine site and a Bidders’ Conference held in Yellowknife. Fairness related comments were provided and appropriate action taken by project officials. 

The RFP closed on August 12, 2013.

FM Activities and Findings during the Evaluation Phase

On August 20, 2013 and August 21, 2013, we observed the consensus evaluation by the evaluation committee of the responses in the four proposals received in response to the mandatory and rated requirements specified in the RFP and provided fairness related comments to the Contracting Authority.  No fairness deficiencies were identified

On August 21, 2013 we also observed the financial evaluation of the two proposals that met the minimum mandatory score requirement and the application of the basis of selection specified in the RFP.  Fairness related comments were provided and appropriate action taken.   No fairness deficiencies were identified

Note: For all references in this report concerning fairness related comments being provided to project officials, it is confirmed that, as necessary, project officials provided clarification to the Fairness Monitor or took appropriate action to address the comments, and as a result no fairness deficiencies were recorded.

Reference Documents

The following documents are referenced by number in this report. Unless otherwise indicated, these documents are available through the Giant Mine Remediation project office.

Table Summary

The following table includes a list of documents referred to in the report such as the RFP, amendments, clarification letters, debriefing letters, etc. Each row is numbered, followed by the document title, then a document identifier such as a date or document number.

No. Document Additional information
1 Request for Proposal (RFP) Published on Buy and Sell on June 27, 2013
2 Amendment 1 to RFP Published on Buy and Sell on July 15, 2013
3 Amendment 2 to RFP Published on Buy and Sell on July 25, 2013
4 Amendment 3 to RFP Published on Buy and Sell on August 1, 2013

Addendum to the Final Report
January 20, 2014

Addendum to Fairness Monitor Contractor’s Final Report dated September 9, 2013 concerning Civil Design Services for the Giant Mine Remediation Project

This Addendum to the Fairness Monitor Contractor’s Final Report covers the period following the conclusion of the evaluation phase and includes contract award and debriefings of bidders.

A contract was awarded to the successful bidder on December 10, 2013 and we reviewed the individual letters forwarded to the successful and unsuccessful bidders on the same day.  Each letter provided comprehensive details of the evaluation results of the respective proposal and an invitation to contact the Contracting Authority if further information was required. On December 18, 2013 we monitored by teleconference the debriefing of one unsuccessful bidder.  On January 10, 2014 we were informed by project officials that no additional requests from bidders had been received for further information.  No fairness deficiencies were identified.

Fairness Monitor Attestation of Assurance

It is the opinion of the Fairness Monitor that the post evaluation activities, including the written and teleconference debriefings, were carried out in a fair manner. In this context, fairness is defined as decisions made objectively, free from personal favouritism and political influence, and encompasses the elements of openness, competitiveness, transparency and compliance.

______________________________
Roger Bridges
President, Knowles Consultancy Services Inc.
FM Contractor's Representative

_______________________________
Peter Woods
FM Specialist

_____________________________
Bruce Maynard P.Eng.
FM Team Leader