Financial reporting—The Long Term Vision and Plan Annual Report 2015 to 2016
Total program expenditures
Figure 21—Total Long Term Vision and Plan Program expenditures (in millions of dollars)
Budget | Expenditures | Forecast | ||||||
---|---|---|---|---|---|---|---|---|
Programs | Project approval | Expenditure authority | 2015 to 2016 budget |
2015 to 2016 expenditures |
Prior years expenditures | Cumulative expenditures up to 2015 to 2016 | Planned expenditures 2016 to 2017 Footnote 2 |
Planned expenditures 2017 to 2018 and future years Footnote 2 |
Total Major capital program Footnote 1 |
2,659.2 | 2,504.4 | 346.6 | 328.0 | 1,483.3 | 1,811.4 | 289.6 | 557.7 |
Total Recapitalization program | 255.0 | 254.0 | 23.8 | 23.6 | 147.3 | 170.9 | 21.0 | 5.8 |
Total Building Components and Connectivity program | 156.1 | 142.2 | 19.5 | 23.1 | 100.9 | 124.0 | 16.3 | 6.5 |
Total Planning program | 145.7 | 80.0 | 18.1 | 13.1 | 47.6 | 60.7 | 12.9 | 10.1 |
Grand total Long Term Vision and Plan (LTVP) | 3,215.9 | 2,980.6 | 408.0 | 387.8 | 1,779.1 | 2,167.0 | 339.8 | 580.1 |
Remarks: Numbers may not add up due to rounding. Planned forecasts may require project approval and/or expenditure authority amendment.
Major capital program
Figure 22—Major capital program project expenditures (in millions of dollars) and delivery timelines
Budget | Expenditures | Forecast | Construction completion dates Footnote 3 |
||||||
---|---|---|---|---|---|---|---|---|---|
Projects | Project approval | Expenditure authority | 2015 to 2016 budget |
2015 to 2016 expenditures |
Prior years expenditures | Cumulative expenditures up to 2015 to 2016 | Planned expenditures 2016 to 2017 Footnote 2 |
Planned expenditures 2017 to 2018 and future years Footnote 2 |
|
West Block rehabilitation | 862.9 | 862.9 | 156.9 | 134.9 | 342.3 | 477.2 | 160.0 | 225.7 | 2017 |
Wellington Building renovation | 425.2 | 425.2 | 95.0 | 95.1 | 298.9 | 394.0 | 22.5 | 8.7 | 2016 |
Visitor Welcome Centre—phase 1 Footnote 4 |
129.9 | 129.9 | 14.7 | 14.7 | 19.6 | 34.3 | 23.0 | 72.6 | 2017 |
Senate interim accommodations (Government Conference Centre) | 273.3 | 223.6 | 36.5 | 36.8 | 19.3 | 56.1 | 35.0 | 173.2 | 2018 |
East Block 1867 wing exterior rehabilitation | 185.6 | 82.7 | 8.0 | 8.2 | 18.3 | 26.4 | 6.0 | 50.2 | TBD |
Sir John A. Macdonald Building | 99.5 | 99.5 | 5.3 | 5.1 | 93.2 | 98.3 | 1.2 | 0.0 | 2015 |
Library of Parliament | 134.1 | 134.1 | 0.0 | 0.0 | 134.1 | 134.1 | 0.0 | 0.0 | 2006 |
Parliament Hill emergency power | 9.7 | 9.7 | 0.9 | 1.2 | 0.0 | 1.2 | 8.5 | 0.0 | 2017 |
Perimeter safety hoarding and overhead protection | 2.0 | 2.0 | 0.0 | 0.8 | 0.8 | 1.7 | 0.0 | 0.0 | 2015 |
Leases, fit-ups and others Footnote 1 |
537.0 | 534.9 | 29.4 | 31.3 | 556.8 | 588.1 | 33.4 | 27.2 | N/A |
Total Major capital program | 2,659.2 | 2,504.4 | 346.6 | 328.0 | 1,483.3 | 1,811.4 | 289.6 | 557.7 | N/A |
Remarks: Numbers may not add up due to rounding. Planned forecasts may require project approval and/or expenditure authority amendment.
Figure 23—Major capital program project spending—Fiscal year 2015 to 2016 (in millions of dollars)
![Figure 23—Major capital program project spending—Fiscal year 2015 to 2016 (in millions of dollars) - See description below.](images/fig23-eng.jpg)
Table equivalent of figure 23—Major capital program project spending—Fiscal year 2015 to 2016 (in millions of dollars)
Project approval | Expenditure authority | Fiscal year 2015 to 2016 budget | Fiscal year 2015 to 2016 expenditures | Overall expenditures to date | |
---|---|---|---|---|---|
West Block rehabilitation | $862.9 | $862.9 | $156.9 | $134.9 | $477.2 |
Wellington Building renovation | $425.2 | $425.2 | $95.0 | $95.1 | $394.0 |
Visitor Welcome Centre—phase 1 | $129.9 | $129.9 | $14.7 | $14.7 | $34.3 |
Senate interim accommodations (Government Conference Centre) | $273.3 | $223.6 | $36.5 | $36.8 | $56.1 |
East Block 1867 wing exterior rehabilitation | $185.6 | $82.7 | $8.0 | $8.2 | $26.4 |
Sir John A. Macdonald Building | $99.5 | $99.5 | $5.3 | $5.1 | $98.3 |
Parliament Hill emergency power | $9.7 | $9.7 | $0.9 | $1.2 | $1.2 |
Perimeter safety hoarding and overhead protection | $2.0 | $2.0 | $0.0 | $0.8 | $1.7 |
Recapitalization program
Figure 24—Recapitalization program project expenditures (in millions of dollars) and delivery timelines
Budget | Expenditures | Forecast | Construction completion dates Footnote 3 |
||||||
---|---|---|---|---|---|---|---|---|---|
Projects | Project approval | Expenditure authority | 2015 to 2016 budget |
2015 to 2016 expenditures |
Prior years expenditures | Cumulative expenditures up to 2015 to 2016 | Planned expenditures 2016 to 2017 Footnote 2 |
Planned expenditures 2017 to 2018 and future years Footnote 2 |
|
Centre Block ventilation towers envelope rehabilitation | 21.3 | 21.3 | 6.9 | 6.8 | 8.5 | 15.3 | 6.0 | 0.0 | 2016 |
Centre Block East and West Pavilions envelope rehabilitation | 17.1 | 17.1 | 5.7 | 5.6 | 7.5 | 13.1 | 4.0 | 0.0 | 2016 |
Centre Block various short-term repairs | 6.4 | 6.4 | 0.4 | 0.4 | 4.6 | 5.0 | 0.0 | 0.0 | 2015 |
Centre Block House of Commons Chamber modifications | 3.5 | 3.5 | 0.9 | 0.9 | 1.6 | 2.5 | 0.0 | 0.0 | 2015 |
Confederation Building high/ low voltage system | 4.1 | 4.1 | 1.7 | 1.7 | 0.6 | 2.2 | 1.9 | 0.0 | 2016 |
Confederation Building window frame stabilization and sash rehabilitation | 7.8 | 7.8 | 3.1 | 3.1 | 1.4 | 4.5 | 3.4 | 0.0 | 2016 |
North perimeter wall rehabilitation Parliament Hill grounds | 16.8 | 16.8 | 3.8 | 3.8 | 8.9 | 12.7 | 4.1 | 0.0 | 2016 |
West slope infrastructure rehabilitation | 10.3 | 10.3 | 1.3 | 1.3 | 8.7 | 10.0 | 0.3 | 0.0 | 2016 |
Other Recapitalization | 167.7 | 166.7 | 0.0 | 0.0 | 105.6 | 105.6 | 1.4 | 5.8 | N/A |
Total Recapitalization program | 255.0 | 254.0 | 23.8 | 23.6 | 147.3 | 170.9 | 21.0 | 5.8 | N/A |
Remarks: Numbers may not add up due to rounding. Planned forecasts may require project approval and/or expenditure authority amendment.
Figure 25—Recapitalization program project spending—Fiscal year 2015 to 2016 (in millions of dollars)
![Figure 25—Recapitalization program project spending—Fiscal year 2015 to 2016 (in millions of dollars) - See description below.](images/fig25-eng.jpg)
Table equivalent of figure 25—Recapitalization program project spending—Fiscal year 2015 to 2016 (in millions of dollars)
Project approval | Expenditure authority | Fiscal year 2015 to 2016 budget | Fiscal year 2015 to 2016 expenditures | Overall expenditures to date | |
---|---|---|---|---|---|
Centre Block ventilation towers envelope rehabilitation | $21.3 | $21.3 | $6.9 | $6.8 | $15.3 |
Centre Block East and West Pavilions envelope rehabilitation | $17.1 | $17.1 | $5.7 | $5.6 | $13.1 |
Centre Block various short-term repairs | $6.4 | $6.4 | $0.4 | $0.4 | $5.0 |
Centre Block House of Commons Chamber modifications | $3.5 | $3.5 | $0.9 | $0.9 | $2.5 |
Confederation Building high/low voltage system | $4.1 | $4.1 | $1.7 | $1.7 | $2.2 |
Confederation Building window frame stabilization and sash rehabilitation | $7.8 | $7.8 | $3.1 | $3.1 | $4.5 |
North perimeter wall rehabilitation Parliament Hill grounds | $16.8 | $16.8 | $3.8 | $3.8 | $12.7 |
West slope infrastructure rehabilitation | $10.3 | $10.3 | $1.3 | $1.3 | $10.0 |
Building Components and Connectivity program
Figure 26—Building Components and Connectivity program project expenditures (in millions of dollars) and delivery timelines
Budget | Expenditures | Forecast | Construction completion dates Footnote 3 |
||||||
---|---|---|---|---|---|---|---|---|---|
Projects | Project approval | Expenditure authority | 2015 to 2016 budget |
2015 to 2016 expenditures |
Prior years expenditures | Cumulative expenditures up to 2015 to 2016 | Planned expenditures 2016 to 2017 Footnote 2 |
Planned expenditures 2017 to 2018 and future years Footnote 2 |
|
Wireless networking | 10.1 | 10.1 | 2.8 | 3.3 | 4.9 | 8.2 | 1.8 | 0.1 | 2017 |
Trunked radio communication system | 15.9 | 15.9 | 2.3 | 2.7 | 12.6 | 15.3 | 0.6 | 0.1 | 2016 |
Integrated security system upgrade and expansion | 16.8 | 16.8 | 1.8 | 2.1 | 9.6 | 11.7 | 5.1 | 0.0 | 2017 |
Core network infrastructure revision Footnote 6 |
11.8 | 11.8 | 3.9 | 4.7 | 5.0 | 9.7 | 2.0 | 0.2 | 2017 |
Parliament Hill pathway connectivity | 15.5 | 15.5 | 1.3 | 1.6 | 11.2 | 12.8 | 0.3 | 2.4 | 2018 |
Next generation network infrastructure—telephony | 11.9 | 5.6 | 2.2 | 2.6 | 0.0 | 2.6 | 3.0 | 0.0 | 2018 |
Master control and distribution upgrade | 6.0 | 6.0 | 4.5 | 5.3 | 0.0 | 5.3 | 0.6 | 0.0 | 2016 |
Other Building Components and Connectivity | 68.1 | 60.5 | 0.7 | 0.8 | 57.6 | 58.4 | 3.0 | 3.8 | N/A |
Total Building Components and Connectivity program | 156.1 | 142.2 | 19.5 | 23.1 | 100.9 | 124.0 | 16.3 | 6.5 | N/A |
Remarks: Numbers may not add up due to rounding. Planned forecasts may require project approval and/or expenditure authority amendment.
Figure 27—Building Components and Connectivity program project spending—Fiscal year 2015 to 2016 (in millions of dollars) and delivery timelines
![Figure 27—Building Components and Connectivity program project spending—Fiscal year 2015 to 2016 (in millions of dollars) and delivery timelines - See description below.](images/fig27-eng.jpg)
Table equivalent of figure 27—Building Components and Connectivity program project spending—Fiscal year 2015 to 2016 (in millions of dollars) and delivery timelines
Project approval | Expenditure authority | Fiscal year 2015 to 2016 budget | Fiscal year 2015 to 2016 expenditures | Overall expenditures to date | |
---|---|---|---|---|---|
Wireless networking | $10.1 | $10.1 | $2.8 | $3.3 | $8.2 |
Trunked radio communication system | $15.9 | $15.9 | $2.3 | $2.7 | $15.3 |
Integrated security system upgrade and expansion | $16.8 | $16.8 | $1.8 | $2.1 | $11.7 |
Core network infrastructure revision | $11.8 | $11.8 | $3.9 | $4.7 | $9.7 |
Parliament Hill pathway connectivity | $15.5 | $15.5 | $1.3 | $1.6 | $12.8 |
Next generation network infrastructure—telephony | $11.9 | $5.6 | $2.2 | $2.6 | $2.6 |
Master control and distribution upgrade | $6.0 | $6.0 | $4.5 | $5.3 | $5.3 |
Planning program
Figure 28—Planning program project expenditures (in millions of dollars) and delivery timelines
Budget | Expenditures | Forecast | Completion dates Footnote 3 |
||||||
---|---|---|---|---|---|---|---|---|---|
Projects | Project approval | Expenditure authority | 2015 to 2016 budget |
2015 to 2016 expenditures |
Prior years expenditures | Cumulative expenditures up to 2015 to 2016 | Planned expenditures 2016 to 2017 Footnote 2 |
Planned expenditures 2017 to 2018 and future years Footnote 2 |
|
Centre Block major rehabilitation | 31.9 | 31.9 | 8.0 | 8.0 | 18.8 | 26.9 | 7.5 | 0.3 | TBD |
Long Term Vision and Plan strategic planning | 10.7 | 10.7 | 6.5 | 3.2 | 7.4 | 10.7 | 2.8 | 2.8 | Ongoing |
Long Term Vision and Plan underground infrastructure master plan | 2.2 | 2.2 | 0.4 | 0.2 | 1.1 | 1.3 | 0.8 | 0.1 | 2016 |
Material management master plan | 1.7 | 1.7 | 0.5 | 0.2 | 1.0 | 1.2 | 0.4 | 0.1 | 2016 |
Long Term Vision and Plan Program Management Office | 2.3 | 2.3 | 2.4 | 1.2 | 0.0 | 1.2 | 1.1 | 0.0 | Ongoing |
Other Planning | 97.0 | 31.3 | 0.3 | 0.2 | 19.3 | 19.4 | 0.3 | 6.8 | N/A |
Total Planning program | 145.7 | 80.0 | 18.1 | 13.1 | 47.6 | 60.7 | 12.9 | 10.1 | N/A |
Remarks: Numbers may not add up due to rounding. Planned forecasts may require project approval and/or expenditure authority amendment.
Figure 29—Planning program project spending—Fiscal year 2015 to 2016 (in millions of dollars)
![Figure 29—Planning program project spending—Fiscal year 2015 to 2016 (in millions of dollars) - See description below.](images/fig29-eng.jpg)
Table equivalent of figure 29—Planning program project spending—Fiscal year 2015 to 2016 (in millions of dollars)
Project approval | Expenditure authority | Fiscal year 2015 to 2016 budget | Fiscal year 2015 to 2016 expenditures | Overall expenditures to date | |
---|---|---|---|---|---|
Centre Block major rehabilitation | $31.9 | $31.9 | $8.0 | $8.0 | $26.9 |
Long Term Vision and Plan strategic planning | $10.7 | $10.7 | $6.5 | $3.2 | $10.7 |
Long Term Vision and Plan underground infrastructure master plan | $2.2 | $2.2 | $0.4 | $0.2 | $1.3 |
Material management master plan | $1.7 | $1.7 | $0.5 | $0.2 | $1.2 |
Long Term Vision and Plan Program Management Office | $2.3 | $2.3 | $2.4 | $1.2 | $1.2 |
Leased
Figure 30—Long Term Vision and Plan lease cost breakdown (in millions of dollars)
LTVP leases | Lease project approval (LPA) Footnote 5 |
Prior years expenditures | Forecast expenditures 2015 to 2016 |
Actual expenditures 2015 to 2016 |
Total expenditures to the end of 2015 to 2016 |
---|---|---|---|---|---|
119 Queen Street | $1.2 | $2.2 | $0.4 | $0.4 | $2.6 |
131 Queen Street | $166.3 | $112.5 | $13.5 | $14.4 | $126.9 |
181 Queen Street | $59.9 | $69.5 | $6.8 | $6.8 | $76.3 |
155 Queen Street (10th Floor) | $13.6 | $2.9 | $0.6 | $0.6 | $3.5 |
155 Queen Street (6th Floor) | $0.3 | $0.1 | $0.1 | $0.1 | $0.2 |
2074-2086 Walkley Road, Trade Shops | $11.2 | $2.8 | $0.7 | $0.6 | $3.3 |
768 Belfast Road, House of Commons | $2.0 | $1.4 | $0.0 | $0.0 | $1.4 |
2455 Don Reid Drive, E-Printing | $11.1 | $4.6 | $1.2 | $1.0 | $5.6 |
1 Wellington Street—Rideau Committee Rooms | $23.6 | $5.1 | $1.0 | $0.9 | $6.1 |
C.D. Howe Building | $18.4 | $14.3 | $1.7 | $1.7 | $16.1 |
Clarica / Sun Life Building | $46.9 | $29.9 | $3.3 | $4.3 | $34.2 |
Interim Room 200—Government of Canada Conference Centre | $9.1 | $8.0 | $0.5 | $0.5 | $8.5 |
Total-LTVP | $363.5 | $253.4 | $29.8 | $31.3 | $284.7 |
Remarks: Numbers may not add up due to rounding.
Figure 31—Annual lease costs (in millions of dollars)
Year | Expenditures | Forecast |
---|---|---|
2002 to 2003 | $0.0 | N/A |
2003 to 2004 | $0.5 | N/A |
2004 to 2005 | $5.5 | N/A |
2005 to 2006 | $6.8 | N/A |
2006 to 2007 | $17.5 | N/A |
2007 to 2008 | $24.0 | N/A |
2008 to 2009 | $24.0 | N/A |
2009 to 2010 | $26.0 | N/A |
2010 to 2011 | $28.1 | N/A |
2011 to 2012 | $29.3 | N/A |
2012 to 2013 | $30.7 | N/A |
2013 to 2014 | $30.5 | N/A |
2014 to 2015 | $30.7 | N/A |
2015 to 2016 | $31.3 | N/A |
2016 to 2017 | N/A | $30.3 |