Financial reporting—The Long Term Vision and Plan Annual Report 2015 to 2016

Document navigation for "The Long Term Vision and Plan Annual Report 2015 to 2016"

Total program expenditures

Figure 21—Total Long Term Vision and Plan Program expenditures (in millions of dollars)

  Budget Expenditures Forecast
Programs Project approval Expenditure authority 2015 to 2016
budget
2015 to 2016
expenditures
Prior years expenditures Cumulative expenditures up to 2015 to 2016 Planned expenditures 2016 to 2017
Footnote 2
Planned expenditures 2017 to 2018 and future years
Footnote 2
Total Major capital program
Footnote 1
2,659.2 2,504.4 346.6 328.0 1,483.3 1,811.4 289.6 557.7
Total Recapitalization program 255.0 254.0 23.8 23.6 147.3 170.9 21.0 5.8
Total Building Components and Connectivity program 156.1 142.2 19.5 23.1 100.9 124.0 16.3 6.5
Total Planning program 145.7 80.0 18.1 13.1 47.6 60.7 12.9 10.1
Grand total Long Term Vision and Plan (LTVP) 3,215.9 2,980.6 408.0 387.8 1,779.1 2,167.0 339.8 580.1

Remarks: Numbers may not add up due to rounding. Planned forecasts may require project approval and/or expenditure authority amendment.

Major capital program

Figure 22—Major capital program project expenditures (in millions of dollars) and delivery timelines

  Budget Expenditures Forecast Construction completion dates
Footnote 3
Projects Project approval Expenditure authority 2015 to 2016
budget
2015 to 2016
expenditures
Prior years expenditures Cumulative expenditures up to 2015 to 2016 Planned expenditures 2016 to 2017
Footnote 2
Planned expenditures 2017 to 2018 and future years
Footnote 2
West Block rehabilitation 862.9 862.9 156.9 134.9 342.3 477.2 160.0 225.7 2017
Wellington Building renovation 425.2 425.2 95.0 95.1 298.9 394.0 22.5 8.7 2016
Visitor Welcome Centre—phase 1
Footnote 4
129.9 129.9 14.7 14.7 19.6 34.3 23.0 72.6 2017
Senate interim accommodations (Government Conference Centre) 273.3 223.6 36.5 36.8 19.3 56.1 35.0 173.2 2018
East Block 1867 wing exterior rehabilitation 185.6 82.7 8.0 8.2 18.3 26.4 6.0 50.2 TBD
Sir John A. Macdonald Building 99.5 99.5 5.3 5.1 93.2 98.3 1.2 0.0 2015
Library of Parliament 134.1 134.1 0.0 0.0 134.1 134.1 0.0 0.0 2006
Parliament Hill emergency power 9.7 9.7 0.9 1.2 0.0 1.2 8.5 0.0 2017
Perimeter safety hoarding and overhead protection 2.0 2.0 0.0 0.8 0.8 1.7 0.0 0.0 2015
Leases, fit-ups and others
Footnote 1
537.0 534.9 29.4 31.3 556.8 588.1 33.4 27.2 N/A
Total Major capital program 2,659.2 2,504.4 346.6 328.0 1,483.3 1,811.4 289.6 557.7 N/A

Remarks: Numbers may not add up due to rounding. Planned forecasts may require project approval and/or expenditure authority amendment.

Figure 23—Major capital program project spending—Fiscal year 2015 to 2016 (in millions of dollars)

Figure 23—Major capital program project spending—Fiscal year 2015 to 2016 (in millions of dollars) - See description below.
Table equivalent of figure 23—Major capital program project spending—Fiscal year 2015 to 2016 (in millions of dollars)
  Project approval Expenditure authority Fiscal year 2015 to 2016 budget Fiscal year 2015 to 2016 expenditures Overall expenditures to date
West Block rehabilitation $862.9 $862.9 $156.9 $134.9 $477.2
Wellington Building renovation $425.2 $425.2 $95.0 $95.1 $394.0
Visitor Welcome Centre—phase 1 $129.9 $129.9 $14.7 $14.7 $34.3
Senate interim accommodations (Government Conference Centre) $273.3 $223.6 $36.5 $36.8 $56.1
East Block 1867 wing exterior rehabilitation $185.6 $82.7 $8.0 $8.2 $26.4
Sir John A. Macdonald Building $99.5 $99.5 $5.3 $5.1 $98.3
Parliament Hill emergency power $9.7 $9.7 $0.9 $1.2 $1.2
Perimeter safety hoarding and overhead protection $2.0 $2.0 $0.0 $0.8 $1.7

Recapitalization program

Figure 24—Recapitalization program project expenditures (in millions of dollars) and delivery timelines

  Budget Expenditures Forecast Construction completion dates
Footnote 3
Projects Project approval Expenditure authority 2015 to 2016
budget
2015 to 2016
expenditures
Prior years expenditures Cumulative expenditures up to 2015 to 2016 Planned expenditures 2016 to 2017
Footnote 2
Planned expenditures 2017 to 2018 and future years
Footnote 2
Centre Block ventilation towers envelope rehabilitation 21.3 21.3 6.9 6.8 8.5 15.3 6.0 0.0 2016
Centre Block East and West Pavilions envelope rehabilitation 17.1 17.1 5.7 5.6 7.5 13.1 4.0 0.0 2016
Centre Block various short-term repairs 6.4 6.4 0.4 0.4 4.6 5.0 0.0 0.0 2015
Centre Block House of Commons Chamber modifications 3.5 3.5 0.9 0.9 1.6 2.5 0.0 0.0 2015
Confederation Building high/ low voltage system 4.1 4.1 1.7 1.7 0.6 2.2 1.9 0.0 2016
Confederation Building window frame stabilization and sash rehabilitation 7.8 7.8 3.1 3.1 1.4 4.5 3.4 0.0 2016
North perimeter wall rehabilitation Parliament Hill grounds 16.8 16.8 3.8 3.8 8.9 12.7 4.1 0.0 2016
West slope infrastructure rehabilitation 10.3 10.3 1.3 1.3 8.7 10.0 0.3 0.0 2016
Other Recapitalization 167.7 166.7 0.0 0.0 105.6 105.6 1.4 5.8 N/A
Total Recapitalization program 255.0 254.0 23.8 23.6 147.3 170.9 21.0 5.8 N/A

Remarks: Numbers may not add up due to rounding. Planned forecasts may require project approval and/or expenditure authority amendment.

Figure 25—Recapitalization program project spending—Fiscal year 2015 to 2016 (in millions of dollars)

Figure 25—Recapitalization program project spending—Fiscal year 2015 to 2016 (in millions of dollars) - See description below.
Table equivalent of figure 25—Recapitalization program project spending—Fiscal year 2015 to 2016 (in millions of dollars)
  Project approval Expenditure authority Fiscal year 2015 to 2016 budget Fiscal year 2015 to 2016 expenditures Overall expenditures to date
Centre Block ventilation towers envelope rehabilitation $21.3 $21.3 $6.9 $6.8 $15.3
Centre Block East and West Pavilions envelope rehabilitation $17.1 $17.1 $5.7 $5.6 $13.1
Centre Block various short-term repairs $6.4 $6.4 $0.4 $0.4 $5.0
Centre Block House of Commons Chamber modifications $3.5 $3.5 $0.9 $0.9 $2.5
Confederation Building high/low voltage system $4.1 $4.1 $1.7 $1.7 $2.2
Confederation Building window frame stabilization and sash rehabilitation $7.8 $7.8 $3.1 $3.1 $4.5
North perimeter wall rehabilitation Parliament Hill grounds $16.8 $16.8 $3.8 $3.8 $12.7
West slope infrastructure rehabilitation $10.3 $10.3 $1.3 $1.3 $10.0

Building Components and Connectivity program

Figure 26—Building Components and Connectivity program project expenditures (in millions of dollars) and delivery timelines

  Budget Expenditures Forecast Construction completion dates
Footnote 3
Projects Project approval Expenditure authority 2015 to 2016
budget
2015 to 2016
expenditures
Prior years expenditures Cumulative expenditures up to 2015 to 2016 Planned expenditures 2016 to 2017
Footnote 2
Planned expenditures 2017 to 2018 and future years
Footnote 2
Wireless networking 10.1 10.1 2.8 3.3 4.9 8.2 1.8 0.1 2017
Trunked radio communication system 15.9 15.9 2.3 2.7 12.6 15.3 0.6 0.1 2016
Integrated security system upgrade and expansion 16.8 16.8 1.8 2.1 9.6 11.7 5.1 0.0 2017
Core network infrastructure revision
Footnote 6
11.8 11.8 3.9 4.7 5.0 9.7 2.0 0.2 2017
Parliament Hill pathway connectivity 15.5 15.5 1.3 1.6 11.2 12.8 0.3 2.4 2018
Next generation network infrastructure—telephony 11.9 5.6 2.2 2.6 0.0 2.6 3.0 0.0 2018
Master control and distribution upgrade 6.0 6.0 4.5 5.3 0.0 5.3 0.6 0.0 2016
Other Building Components and Connectivity 68.1 60.5 0.7 0.8 57.6 58.4 3.0 3.8 N/A
Total Building Components and Connectivity program 156.1 142.2 19.5 23.1 100.9 124.0 16.3 6.5 N/A

Remarks: Numbers may not add up due to rounding. Planned forecasts may require project approval and/or expenditure authority amendment.

Figure 27—Building Components and Connectivity program project spending—Fiscal year 2015 to 2016 (in millions of dollars) and delivery timelines

Figure 27—Building Components and Connectivity program project spending—Fiscal year 2015 to 2016 (in millions of dollars) and delivery timelines - See description below.
Table equivalent of figure 27—Building Components and Connectivity program project spending—Fiscal year 2015 to 2016 (in millions of dollars) and delivery timelines
  Project approval Expenditure authority Fiscal year 2015 to 2016 budget Fiscal year 2015 to 2016 expenditures Overall expenditures to date
Wireless networking $10.1 $10.1 $2.8 $3.3 $8.2
Trunked radio communication system $15.9 $15.9 $2.3 $2.7 $15.3
Integrated security system upgrade and expansion $16.8 $16.8 $1.8 $2.1 $11.7
Core network infrastructure revision $11.8 $11.8 $3.9 $4.7 $9.7
Parliament Hill pathway connectivity $15.5 $15.5 $1.3 $1.6 $12.8
Next generation network infrastructure—telephony $11.9 $5.6 $2.2 $2.6 $2.6
Master control and distribution upgrade $6.0 $6.0 $4.5 $5.3 $5.3

Planning program

Figure 28—Planning program project expenditures (in millions of dollars) and delivery timelines

  Budget Expenditures Forecast Completion dates
Footnote 3
Projects Project approval Expenditure authority 2015 to 2016
budget
2015 to 2016
expenditures
Prior years expenditures Cumulative expenditures up to 2015 to 2016 Planned expenditures 2016 to 2017
Footnote 2
Planned expenditures 2017 to 2018 and future years
Footnote 2
Centre Block major rehabilitation 31.9 31.9 8.0 8.0 18.8 26.9 7.5 0.3 TBD
Long Term Vision and Plan strategic planning 10.7 10.7 6.5 3.2 7.4 10.7 2.8 2.8 Ongoing
Long Term Vision and Plan underground infrastructure master plan 2.2 2.2 0.4 0.2 1.1 1.3 0.8 0.1 2016
Material management master plan 1.7 1.7 0.5 0.2 1.0 1.2 0.4 0.1 2016
Long Term Vision and Plan Program Management Office 2.3 2.3 2.4 1.2 0.0 1.2 1.1 0.0 Ongoing
Other Planning 97.0 31.3 0.3 0.2 19.3 19.4 0.3 6.8 N/A
Total Planning program 145.7 80.0 18.1 13.1 47.6 60.7 12.9 10.1 N/A

Remarks: Numbers may not add up due to rounding. Planned forecasts may require project approval and/or expenditure authority amendment.

Figure 29—Planning program project spending—Fiscal year 2015 to 2016 (in millions of dollars)

Figure 29—Planning program project spending—Fiscal year 2015 to 2016 (in millions of dollars) - See description below.
Table equivalent of figure 29—Planning program project spending—Fiscal year 2015 to 2016 (in millions of dollars)
  Project approval Expenditure authority Fiscal year 2015 to 2016 budget Fiscal year 2015 to 2016 expenditures Overall expenditures to date
Centre Block major rehabilitation $31.9 $31.9 $8.0 $8.0 $26.9
Long Term Vision and Plan strategic planning $10.7 $10.7 $6.5 $3.2 $10.7
Long Term Vision and Plan underground infrastructure master plan $2.2 $2.2 $0.4 $0.2 $1.3
Material management master plan $1.7 $1.7 $0.5 $0.2 $1.2
Long Term Vision and Plan Program Management Office $2.3 $2.3 $2.4 $1.2 $1.2

Leased

Figure 30—Long Term Vision and Plan lease cost breakdown (in millions of dollars)

LTVP leases Lease project approval (LPA)
Footnote 5
Prior years expenditures Forecast expenditures
2015 to 2016
Actual expenditures
2015 to 2016
Total expenditures to
the end of 2015 to 2016
119 Queen Street $1.2 $2.2 $0.4 $0.4 $2.6
131 Queen Street $166.3 $112.5 $13.5 $14.4 $126.9
181 Queen Street $59.9 $69.5 $6.8 $6.8 $76.3
155 Queen Street (10th Floor) $13.6 $2.9 $0.6 $0.6 $3.5
155 Queen Street (6th Floor) $0.3 $0.1 $0.1 $0.1 $0.2
2074-2086 Walkley Road, Trade Shops $11.2 $2.8 $0.7 $0.6 $3.3
768 Belfast Road, House of Commons $2.0 $1.4 $0.0 $0.0 $1.4
2455 Don Reid Drive, E-Printing $11.1 $4.6 $1.2 $1.0 $5.6
1 Wellington Street—Rideau Committee Rooms $23.6 $5.1 $1.0 $0.9 $6.1
C.D. Howe Building $18.4 $14.3 $1.7 $1.7 $16.1
Clarica / Sun Life Building $46.9 $29.9 $3.3 $4.3 $34.2
Interim Room 200—Government of Canada Conference Centre $9.1 $8.0 $0.5 $0.5 $8.5
Total-LTVP $363.5 $253.4 $29.8 $31.3 $284.7

Remarks: Numbers may not add up due to rounding.

Figure 31—Annual lease costs (in millions of dollars)

Year Expenditures Forecast
2002 to 2003 $0.0 N/A
2003 to 2004 $0.5 N/A
2004 to 2005 $5.5 N/A
2005 to 2006 $6.8 N/A
2006 to 2007 $17.5 N/A
2007 to 2008 $24.0 N/A
2008 to 2009 $24.0 N/A
2009 to 2010 $26.0 N/A
2010 to 2011 $28.1 N/A
2011 to 2012 $29.3 N/A
2012 to 2013 $30.7 N/A
2013 to 2014 $30.5 N/A
2014 to 2015 $30.7 N/A
2015 to 2016 $31.3 N/A
2016 to 2017 N/A $30.3